2010
Passenger Terminal: Delivered on schedule. Baggage handling system, air bridge and HVAC system commissioned, building systems being calibrated and tested.
Cargo Terminal: Commissioning of ETV and cargo systems complete, building hand-over and snagging ongoing. Negotiations concluded for V.C.T. Bulk earthworks for V.C.T. development in progress. Tenant fit-out for SAAC and E.A.S. in progress.
Dube TradeZone: Roads and bulk infrastructure complete. Final snagging and hand-over in progress.
Dube TradeHouse development in progress, with building internals commenced. Cargo pallet conveyor bridge-bases complete.
2010
2012
Dube TradePort Corporation official opening by South African President J.G. Zuma
SA Express signs deal with Dube TradePort to launch Durban routes connecting Harare and Lusaka.
2014
Samsung Electronics SA established in Dube TradePort Industrial Development Zone.
2014
2015
Completion of three public infrastructure projects:
2016
In line with precinct expansion, the R200 million International Trade Avenue - a dual carriage highway - was completed providing access between tracts of developable land north of the existing site and the N2 and R102 freeways, via the Watson Highway.
2016
2017
A guardhouse, located in Dube TradeZone 1 was completed. In addition, a warehouse for disaster response organisation, Gift of the Givers, was completed, along with a technical facility, in Dube TradeZone 1, whilst a workshop was established in Dube AgriZone.
The construction of a double basement in Block D, in Dube City, commenced.
Operational investments included:
2018
Projects designed to give effect to electrical infrastructure in Dube TradeZone 1, the fit-out of a One-Stop-Shop satellite centre and Dube TradeZone 1 guardhouse were completed. In addition work on the Hlawe River Trunk Sewer was completed.
Operational Investments included:
2018
2019
The practical completion of Dube AgriZone's water laboratory and technical facility was achieved, whilst an agreement was signed with Mara Phones SA (Pty) Ltd regarding its investment of R1.28 billion in a new facility located within Dube TradeZone 1. Additional investments were made by Monustep and Hodari Properties (Pty) Ltd, who undertook the renovation of an existing facility in order to accommodate a new tenant, Conlog (Pty) Ltd.
Operational Investments included:
2020
Completed projects included:
Operational investment includes:
2020
29° South, 7 Umsinsi Junction
Dube City, La Mercy
KwaZulu-Natal
4399
Tel: +27 32 814 0000
Email: invest@dubetradeport.co.za