It’s all systems go for Dube TradePort
Construction of Dube TradePort, inclusive of the new international airport, is on track for completion by March 2010.
The 55m-high Air Traffic Control Tower was completed in less than 10 days, thanks to the adoption of innovative engineering applications and technology. Conventional construction methods would have resulted in a six to eight-week project.
Meanwhile, the Terminal Building has reached ground level, following extensive piling and the necessary re-inforcement of the basement area. The Cargo Terminal has already reached the first floor level and is on schedule, with both design and cost signed-off.
Earthworks and cut-away work is currently underway on the vital access road between the N2 freeway and Dube TradePort.
The massive undertaking with regard to re-inforcing the runway area is progressing quite steadily, with the final compound mix for the tarred surface area already finalised, while the airport’s on-site reservoir is set for completion by the end of this year, 2008.
Pleasingly, the Trade Zone development is also well on track, with ground work being prepared for levelling and compaction.
Importantly, Dube TradePort achieved a most successful Environmental Impact Assessment audit, undertaken by DEAT in March this year. The only area of concern raised in the assessment was that of dust control and surface erosion. This issue is to be mitigated through the installation of dust monitors and the utilisation of improved drainage engineering applications.
This Engineer, Procure and Construct mega-project requires the Contractor, Ilembe Airport Construction Services (Pty) Ltd., to meet certain Broad-Based Black Economic Empowerment targets set by Airports Company South Africa/Dube TradePort as regards:
- Ownership;
- Management Control;
- Enterprise and Skills Development;
- Preferential Procurement; and
- Local Socio-Economic Impact.
The following comparisons are clearly indicative of the Contractor’s progress to date in this regard.
Local Socio-Economic Impact:
The local socio-economic impact total project target is 0,4% of project turn-over, which is about R27,3 million.
|